Paperwork and pay

Draw schedules on a residential build

A draw schedule maps requests for project funds to agreed progress. Keep the lender draw, owner payment, and subcontract payment schedule distinct.

You need to fund the next phase without leaving completed trades waiting for payment. Build the draw schedule from the loan requirements, construction agreement, and trade commitments. A construction loan typically advances money as work progresses, according to the Consumer Financial Protection Bureau. That funding schedule is one part of the payment plan.

Do not promise a sub that payment arrives “at the next draw” without identifying the trigger and responsibility. Track lender disbursements, owner payments, and amounts you owe subs in separate records.

What a construction draw is

A draw is a disbursement of project funds. For financed residential construction, the CFPB describes a series of loan advances as construction progresses. CFPB construction-loan explanation Ask the borrower and lender how this loan handles those advances.

Confirm who requests funds, who receives them, and which documents the lender requires. Ask whether the lender pays the borrower, builder, or another designated recipient. Get this loan’s written instructions rather than using another builder’s process.

If the owner funds the job without a construction loan, ask what payment milestones the construction agreement uses. Build the schedule from that agreement. A phase label alone does not tell you the agreed amount, required inspection, or payment date.

Define the work and records required for each draw

The custom-homebuilding overview hosted by NAHB describes the broad progression from foundations and framing through rough-ins, interior work, and final stages. It also notes that design and systems affect project details and scheduling. Use that sequence to organize the plan, then check this project’s milestones.

Use this worksheet to discuss milestones with the lender. It assigns no percentage of contract value.

Scroll to read all columns.

Proposed checkpoint Evidence to discuss with lender and owner Trade-payment question
Foundation Which installed work and required records establish completion? When do concrete, excavation, and related bills become due?
Dry-in Which enclosure items must be complete for this draw? Are roofing and window packages billed together or separately?
Rough-in Which trade scopes and inspection records belong in the request? Can each completed trade bill before the others finish?
Drywall and interior progress How is partial progress measured and accepted? Which finish-trade commitments arrive before funding?
Final Which completion and closeout documents release the balance? How are punch items and retained amounts separated?

Ask the lender to approve the milestone descriptions before you use them in the cash plan. Then compare them with the subcontracts. If a trade payment is due before an expected draw, record the funding gap. Do not hide it by changing the subcontract due date in a spreadsheet.

Confirm lender and permit inspection requirements

Ask what event triggers the lender’s inspection or other progress review. Is it a submitted draw request, a scheduled milestone, or another loan condition? Ask the lender how to order the inspection and when to expect a response.

Ask the lender and local inspections department to explain their separate requirements. Do not treat one report as proof that every contractual, permitting, or payment condition is satisfied. Ask each responsible party which evidence it requires, and attach the required record to each request.

The CFPB’s construction-loan disclosure guide discusses inspection and handling fees associated with staged loan disbursements. Confirm the actual loan fees and when they are charged. Include them in the project’s funding worksheet using the lender’s documents, not a guessed allowance.

Build the payment calendar before crews start

Create a calendar with each trade’s billing cutoff, approver, payment trigger, and due date. Add the lender submission dates, required attachments, progress-review steps, and expected funding status. Mark expected dates as forecasts until confirmed.

Give the person preparing the draw a checklist for every submission. Identify missing documents before sending the request. Keep the version submitted, the acknowledgment, questions from the lender, and the approved amount together. Record when funds arrive separately from when they are approved.

AIA’s subcontractor payment-application instructions identify completed and stored work, changes, prior payments, retainage, and the current request as separate information. Check each item separately in your own draw package. Follow your actual agreement and lender requirements rather than assuming an AIA form is required.

Keep change orders in the funding plan

When scope changes, update the forecast and draw request through the required approval process. Identify the changed scope, approved amount, timing effect, and who supplies the added funds. Keep pending proposals separate from signed changes.

Do not count an owner conversation as lender acceptance of an increased loan budget. Ask the lender how it handles changed costs and whether an amended budget or other approval is required. Confirm the answer before making a funding promise to a trade.

For a deleted scope, reconcile the credit and any commitments already made. For added work, compare the procurement date with the approved funding date. If the sub must buy a special-order item before funding arrives, put who covers the gap in the written agreement. Use the change-order guide to organize the scope and approval record.

Check sub payment dates separately from draw dates

North Carolina’s G.S. 22C-3 establishes qualifying pass-through payment timing after upstream receipt. However, G.S. 22C-6 excludes residential contractors and specified residential improvements, including those with twelve or fewer units. Do not apply the chapter automatically to a single-family build.

Use the subcontract payment workflow and invoice-review checklist to track trade commitments beside the funding plan.

Ask a construction attorney which payment rules and contract clauses apply to your subcontracts. Then plan funding to meet those obligations. A “draw pending” entry does not tell you whether the sub’s payment is due under its agreement.

When a draw slips, update the owner and affected trades with verified status. State what has been submitted, what remains outstanding, and who handles the next step. Avoid giving a new payment date before you know how it will be funded. Resolve any amendment with the authorized contracting parties.

Reconcile each draw before requesting the next one

Compare requested, approved, received, and disbursed amounts. Match each trade payment to its invoice. Track retained money and remaining contract balances separately. Mark disputed work as disputed rather than complete.

Compare the work left to finish with the updated schedule and funds available. Ask the owner and lender to address an unexplained shortfall before you commit to the next phase. Check the plan with the lender and your accountant.

For year-end reporting after the payment records are reconciled, follow the subcontractor 1099 workflow.

Where Cercha fits

Cercha Search filters by trade, ZIP code, and radius to help you identify prospective trade partners. Portfolios and endorsements give you context before you discuss a scope. Use Messages to begin that conversation, then agree on payment terms through your contracting process.

. .

More guides: Paperwork and pay

Related guides

Sources

  1. Consumer Financial Protection Bureau. (2024, September 11). What is a construction loan? https://www.consumerfinance.gov/ask-cfpb/what-is-a-construction-loan-en-108/
  2. Consumer Financial Protection Bureau. (2019, December). TILA-RESPA Integrated Disclosures for Construction Loans: Guide for combined, one-transaction disclosures. https://www.consumerfinance.gov/documents/8263/cfpb_trid-combined-construction-loan-guide.pdf
  3. Grand County Builders’ Association. (2021, May 18). Overview to the custom homebuilding process. National Association of Home Builders. https://www.nahb.org/-/media/NAHB/advocacy/docs/industry-issues/disaster-resources/home-building-overview.pdf?rev=6f76493d1a3e493fb717f52f0fa47d7e
  4. AIA Contract Documents. (n.d.). Instructions: G702S–2017, Application and Certificate for Payment, Contractor–Subcontractor Version. Retrieved October 14, 2026, from https://help.aiacontracts.com/hc/en-us/articles/1500009322141-Instructions-G702S-2017-Application-and-Certificate-for-Payment-Contractor-Subcontractor-Version
  5. N.C. Gen. Stat. § 22C-3. https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_22C/GS_22C-3.html
  6. N.C. Gen. Stat. § 22C-6. https://www.ncleg.gov/EnactedLegislation/Statutes/HTML/BySection/Chapter_22C/GS_22C-6.html